We are pleased to report that PACT continues to progress well through the structure of apartment Levels 1 and 2 of the East and Central Buildings while concurrently working on Level 3 amenities, apartments and pool for the East Building.
As the main building structure progresses at pace, PACT has commenced the installation of plumbing, electrical and air-conditioning services to the Ground Floor. This being the initial stages of the building fit-out works.
The Level 3 amenities for the Central Building will commence at the end of June. This is a significant milestone in the development timeline, not only in marking the commencement of the private residential amenities, but also because the East and Central towers sit above Level 3 and will start to emerge in the coming months.
As Rivière rises, it is starting to command the attention of commuters on Canning Bridge and the freeway.